Khabarovsk International Airport. Domestic airlines terminal

Khabarovsk International Airport. Domestic airlines terminal

Client: Khabarovsky Airport, JSC
Services: Project management, Technical Customer (TekhZakazchik), Construction control & QA/QC
Schedule: 2017 – 2019

In the project, we controlled the construction of the following complex of buildings and structures:

  •   terminal for domestic airlines,
  •   station square with driveways for cars and public transport,
  •   parking and pedestrian areas.


Facility’s parameters:

  •   Building area - 27 thousand square meters
  •   5 floors
  •   throughput capacity of the domestic airlines terminal is 3 million passengers per year.

The construction was completed in a short time - 18 months. In many ways, this became possible thanks to the chosen strategy for the implementation of the project, high-quality planning and the use of construction technologies that allow work in the difficult climatic conditions of the Khabarovsk krai.